Transmission Line Switching Studies

Saudi Electricity Company (Saudi Arabia)
AC System Studies

We were contracted by Saudi Electricity Company (SEC) to perform switching studies to identify undesirable conditions in the high voltage network due to switching events including the switching of line end reactors.

The project included approximately 25 separate studies at selected substations (includes over 20 double circuit lines/ cables):

Back